Timnath Parkway. - Buss Grove Rd. to Main St. (CR5)
The Timnath Parkway project will extend Timnath Pkwy. north from Buss Grove Rd. to reconnect with Main St. (CR5), creating an important new link in the Town’s roadway network. This connection will improve mobility, support future development, and provide residents with an new north–south travel option.
The project includes the design and construction of a new two‑lane roadway with a landscaped median and sidewalks to enhance safety and comfort for drivers, pedestrians and cyclists. The corridor will also be built to accommodate the Town’s long‑term vision for an ultimate four‑lane arterial as traffic and community needs grow.
The Timnath Parkway project will extend Timnath Pkwy. north from Buss Grove Rd. to reconnect with Main St. (CR5), creating an important new link in the Town’s roadway network. This connection will improve mobility, support future development, and provide residents with an new north–south travel option.
The project includes the design and construction of a new two‑lane roadway with a landscaped median and sidewalks to enhance safety and comfort for drivers, pedestrians and cyclists. The corridor will also be built to accommodate the Town’s long‑term vision for an ultimate four‑lane arterial as traffic and community needs grow.
-
Project Update: Timnath Parkway Utility Work and Traffic Impacts
Share Project Update: Timnath Parkway Utility Work and Traffic Impacts on Facebook Share Project Update: Timnath Parkway Utility Work and Traffic Impacts on X (formerly Twitter) Share Project Update: Timnath Parkway Utility Work and Traffic Impacts on Linkedin Email Project Update: Timnath Parkway Utility Work and Traffic Impacts linkConstruction continues on the Timnath Parkway - Buss Grove Rd. to Main St. (CR 5) Project following the successful opening of the new roundabout and restoration of two-way traffic.
Traffic Updates
- Intermittent lane closures, traffic shifts and flagging operations will continue as needed throughout construction.
- Utility pole removal is anticipated Thursday, Nov. 19, and Friday, Nov. 20. Temporary traffic stops and lane shifts may be necessary as crews remove overhead utility lines and poles near the roundabout.
- As part of the separate Thornton Waterline Project, Colorado Blvd. is scheduled to remain fully closed north of Wildwing Dr. through Nov. 26. Motorists should plan alternate routes and allow additional travel time.
Remaining Construction Activities
Crews will continue utility relocations, sidewalk improvements, final grading, signage installation, landscaping and other remaining construction activities.
Sidewalks and pedestrian pathways will remain closed where construction is ongoing and will reopen once the remaining work is completed and safe access can be provided.
Anticipated Project Completion
Major roadway improvements are expected to be substantially complete by the end of 2026, with remaining lighting, signage and landscaping work continuing into 2027.
Keeping You Informed
As the project progresses toward completion, website updates will be provided as significant construction activities or traffic changes occur. Please check back for the latest project information.
Project Contact Information
Community members are encouraged to reach out with construction-related questions or concerns.
Project hotline: (970) 795-3302
Project email: timnathparkway@getinfonow.us
Construction schedules are subject to change due to weather, utility coordination or other unforeseen conditions. Motorists and pedestrians are encouraged to follow posted signage and use caution when traveling through the construction area.
Construction continues on the Timnath Parkway - Buss Grove Rd. to Main St. (CR 5) Project following the successful opening of the new roundabout and restoration of two-way traffic.
Traffic Updates
- Intermittent lane closures, traffic shifts and flagging operations will continue as needed throughout construction.
- Utility pole removal is anticipated Thursday, Nov. 19, and Friday, Nov. 20. Temporary traffic stops and lane shifts may be necessary as crews remove overhead utility lines and poles near the roundabout.
- As part of the separate Thornton Waterline Project, Colorado Blvd. is scheduled to remain fully closed north of Wildwing Dr. through Nov. 26. Motorists should plan alternate routes and allow additional travel time.
Remaining Construction Activities
Crews will continue utility relocations, sidewalk improvements, final grading, signage installation, landscaping and other remaining construction activities.
Sidewalks and pedestrian pathways will remain closed where construction is ongoing and will reopen once the remaining work is completed and safe access can be provided.
Anticipated Project Completion
Major roadway improvements are expected to be substantially complete by the end of 2026, with remaining lighting, signage and landscaping work continuing into 2027.
Keeping You Informed
As the project progresses toward completion, website updates will be provided as significant construction activities or traffic changes occur. Please check back for the latest project information.
Project Contact Information
Community members are encouraged to reach out with construction-related questions or concerns.
Project hotline: (970) 795-3302
Project email: timnathparkway@getinfonow.us
Construction schedules are subject to change due to weather, utility coordination or other unforeseen conditions. Motorists and pedestrians are encouraged to follow posted signage and use caution when traveling through the construction area.
-
Project Update: Traffic Changes and Roundabout Opening
Share Project Update: Traffic Changes and Roundabout Opening on Facebook Share Project Update: Traffic Changes and Roundabout Opening on X (formerly Twitter) Share Project Update: Traffic Changes and Roundabout Opening on Linkedin Email Project Update: Traffic Changes and Roundabout Opening linkConstruction continues on the Timnath Parkway - Buss Grove Rd. to Main St. (CR 5) Project, with crews advancing roadway improvements and preparing for upcoming traffic changes.
Traffic Updates
- Timnath Parkway - Buss Grove to Main St.(CR 5) Roundabout –The newly constructed roundabout is anticipated to open to two-way traffic by end of the day on Friday, Nov. 6, weather and construction schedules permitting. This milestone will provide an important connection to Main Street Timnath.
- Buss Grove Rd. and Main St. (CR 5): The intersection is expected to reopen by the end of the day on Friday, Nov. 6.
- Ongoing Traffic Impacts: Motorists may encounter temporary daytime lane shifts, intermittent lane closures and flagging operations as construction continues.
- Colorado Blvd.: As part of the Thornton Waterline Project, Colorado Blvd. will be fully closed north of Wildwing Dr. from Nov. 7 through Nov. 26. Motorists should plan alternate routes and allow additional travel time.
Benefits of Roundabouts
The roundabout is designed to enhance safety, improve traffic flow and strengthen connections throughout the community.
Key benefits include:
- Improved Safety: Reduces the number of potential conflict points between vehicles and lowers the risk of severe crashes compared with traditional intersections.
- Slower, Safer Speeds: Encourages motorists to slow down when entering and navigating the roundabout, helping create a safer environment for all roadway users.
- Efficient Traffic Flow: Keeps vehicles moving through the intersection, reducing unnecessary stops, delays and congestion.
- Pedestrian and Bicycle Safety: Provides designated crossing opportunities and encourages reduced vehicle speeds, improving safety once these facilities are completed and open for use.
- Enhanced Connectivity: Improves connections[KM1] throughout the community, providing better access to local businesses, neighborhoods and surrounding areas.
Remaining Construction Activities
Crews will continue utility relocations, sidewalk improvements, landscaping and other remaining construction activities.
Anticipated Project Completion
Major roadway improvements are expected to be substantially complete by the end of 2026, with remaining lighting, signage and landscaping work continuing into 2027.
Project Contact Information
Community members are encouraged to reach out with construction-related questions or concerns.
Project hotline: (970) 795-3302
Project email: timnathparkway@getinfonow.us
Construction schedules are subject to change due to weather, utility coordination or other unforeseen conditions. Motorists and pedestrians are encouraged to follow posted signage and use caution when traveling through the construction area.
Construction continues on the Timnath Parkway - Buss Grove Rd. to Main St. (CR 5) Project, with crews advancing roadway improvements and preparing for upcoming traffic changes.
Traffic Updates
- Timnath Parkway - Buss Grove to Main St.(CR 5) Roundabout –The newly constructed roundabout is anticipated to open to two-way traffic by end of the day on Friday, Nov. 6, weather and construction schedules permitting. This milestone will provide an important connection to Main Street Timnath.
- Buss Grove Rd. and Main St. (CR 5): The intersection is expected to reopen by the end of the day on Friday, Nov. 6.
- Ongoing Traffic Impacts: Motorists may encounter temporary daytime lane shifts, intermittent lane closures and flagging operations as construction continues.
- Colorado Blvd.: As part of the Thornton Waterline Project, Colorado Blvd. will be fully closed north of Wildwing Dr. from Nov. 7 through Nov. 26. Motorists should plan alternate routes and allow additional travel time.
Benefits of Roundabouts
The roundabout is designed to enhance safety, improve traffic flow and strengthen connections throughout the community.
Key benefits include:
- Improved Safety: Reduces the number of potential conflict points between vehicles and lowers the risk of severe crashes compared with traditional intersections.
- Slower, Safer Speeds: Encourages motorists to slow down when entering and navigating the roundabout, helping create a safer environment for all roadway users.
- Efficient Traffic Flow: Keeps vehicles moving through the intersection, reducing unnecessary stops, delays and congestion.
- Pedestrian and Bicycle Safety: Provides designated crossing opportunities and encourages reduced vehicle speeds, improving safety once these facilities are completed and open for use.
- Enhanced Connectivity: Improves connections[KM1] throughout the community, providing better access to local businesses, neighborhoods and surrounding areas.
Remaining Construction Activities
Crews will continue utility relocations, sidewalk improvements, landscaping and other remaining construction activities.
Anticipated Project Completion
Major roadway improvements are expected to be substantially complete by the end of 2026, with remaining lighting, signage and landscaping work continuing into 2027.
Project Contact Information
Community members are encouraged to reach out with construction-related questions or concerns.
Project hotline: (970) 795-3302
Project email: timnathparkway@getinfonow.us
Construction schedules are subject to change due to weather, utility coordination or other unforeseen conditions. Motorists and pedestrians are encouraged to follow posted signage and use caution when traveling through the construction area.
-
Construction continues on the Timnath Parkway - Buss Grove Rd. to Main St. (CR 5) Project, with ongoing asphalt paving, utility relocations and roadway improvements.
Share Construction continues on the Timnath Parkway - Buss Grove Rd. to Main St. (CR 5) Project, with ongoing asphalt paving, utility relocations and roadway improvements. on Facebook Share Construction continues on the Timnath Parkway - Buss Grove Rd. to Main St. (CR 5) Project, with ongoing asphalt paving, utility relocations and roadway improvements. on X (formerly Twitter) Share Construction continues on the Timnath Parkway - Buss Grove Rd. to Main St. (CR 5) Project, with ongoing asphalt paving, utility relocations and roadway improvements. on Linkedin Email Construction continues on the Timnath Parkway - Buss Grove Rd. to Main St. (CR 5) Project, with ongoing asphalt paving, utility relocations and roadway improvements. linkUpcoming Traffic Changes
- Timnath Parkway: Southbound traffic remains open, while northbound access closed. The project team is working toward restoring two-way traffic by Friday, Nov. 6. Additional temporary traffic restrictions may be necessary as construction and utility work continue.
- Buss Grove Rd. and Main St. (CR 5): The intersection is anticipated to reopen by Nov. 9. Additional temporary closures may be required to complete remaining roadway improvements and utility relocations.
- Colorado Blvd.: As part of the Thornton Waterline Project, Colorado Blvd. will be fully closed north of Wildwing Dr. from Nov. 9 through Nov. 26. Motorists should plan alternate routes and allow additional travel time.
Anticipated Project Completion
Major roadway improvements are expected to be substantially complete by the end of 2026, with remaining lighting, signage and landscaping work continuing into 2027.
Keeping You Informed During Construction
To help keep businesses, residents and motorists informed, the Town of Timnath has expanded its communication efforts to provide timely updates on construction progress, upcoming traffic changes and anticipated project milestones.
Community members are encouraged to reach out with construction-related questions or concerns.
Project hotline: (970) 795-3302
Project email: timnathparkway@getinfonow.us
Construction schedules are subject to change due to weather, utility coordination or other unforeseen conditions. Motorists are encouraged to follow posted signage and use caution when traveling through the construction area.
Upcoming Traffic Changes
- Timnath Parkway: Southbound traffic remains open, while northbound access closed. The project team is working toward restoring two-way traffic by Friday, Nov. 6. Additional temporary traffic restrictions may be necessary as construction and utility work continue.
- Buss Grove Rd. and Main St. (CR 5): The intersection is anticipated to reopen by Nov. 9. Additional temporary closures may be required to complete remaining roadway improvements and utility relocations.
- Colorado Blvd.: As part of the Thornton Waterline Project, Colorado Blvd. will be fully closed north of Wildwing Dr. from Nov. 9 through Nov. 26. Motorists should plan alternate routes and allow additional travel time.
Anticipated Project Completion
Major roadway improvements are expected to be substantially complete by the end of 2026, with remaining lighting, signage and landscaping work continuing into 2027.
Keeping You Informed During Construction
To help keep businesses, residents and motorists informed, the Town of Timnath has expanded its communication efforts to provide timely updates on construction progress, upcoming traffic changes and anticipated project milestones.
Community members are encouraged to reach out with construction-related questions or concerns.
Project hotline: (970) 795-3302
Project email: timnathparkway@getinfonow.us
Construction schedules are subject to change due to weather, utility coordination or other unforeseen conditions. Motorists are encouraged to follow posted signage and use caution when traveling through the construction area.
-
CR 5/Main St. & Buss Grove Rd. Traffic Update (10/21)
Share CR 5/Main St. & Buss Grove Rd. Traffic Update (10/21) on Facebook Share CR 5/Main St. & Buss Grove Rd. Traffic Update (10/21) on X (formerly Twitter) Share CR 5/Main St. & Buss Grove Rd. Traffic Update (10/21) on Linkedin Email CR 5/Main St. & Buss Grove Rd. Traffic Update (10/21) link
Following unanticipated utility delays, work continues on the CR 5/Main Street and Buss Grove Road improvements.
The southbound lane reopened on Oct. 19, with work continuing in that area through Nov. 6. Additional work will continue as crews move through the remaining project items.
Weather and construction delays may impact the schedule. Please drive safely and follow posted traffic control measures.Following unanticipated utility delays, work continues on the CR 5/Main Street and Buss Grove Road improvements.
The southbound lane reopened on Oct. 19, with work continuing in that area through Nov. 6. Additional work will continue as crews move through the remaining project items.
Weather and construction delays may impact the schedule. Please drive safely and follow posted traffic control measures. -
Construction Update: Intersection Closure Scheduled for Next Phase of Work
Share Construction Update: Intersection Closure Scheduled for Next Phase of Work on Facebook Share Construction Update: Intersection Closure Scheduled for Next Phase of Work on X (formerly Twitter) Share Construction Update: Intersection Closure Scheduled for Next Phase of Work on Linkedin Email Construction Update: Intersection Closure Scheduled for Next Phase of Work link
Construction on the Timnath Pkwy. North connection is moving into the next phase, requiring a temporary closure to complete roadway improvements and prepare the area for final paving.
Beginning Sept. 28, the intersection of Buss Grove Rd. and CR 5 will be closed to all through traffic. The closure is anticipated to remain in place through Oct. 9, weather and construction conditions permitting. A signed detour route will be provided for motorists.
Following completion of this phase, the intersection is expected to reopen to traffic on a gravel surface. Final paving operations are currently scheduled for Oct. 11-16, after which the roadway will be opened in its final condition, pending weather or construction delays.
This closure is a necessary step toward completing the intersection improvements and advancing the overall project. Residents and motorists are encouraged to plan ahead and allow additional travel time while work is underway.

Construction on the Timnath Pkwy. North connection is moving into the next phase, requiring a temporary closure to complete roadway improvements and prepare the area for final paving.
Beginning Sept. 28, the intersection of Buss Grove Rd. and CR 5 will be closed to all through traffic. The closure is anticipated to remain in place through Oct. 9, weather and construction conditions permitting. A signed detour route will be provided for motorists.
Following completion of this phase, the intersection is expected to reopen to traffic on a gravel surface. Final paving operations are currently scheduled for Oct. 11-16, after which the roadway will be opened in its final condition, pending weather or construction delays.
This closure is a necessary step toward completing the intersection improvements and advancing the overall project. Residents and motorists are encouraged to plan ahead and allow additional travel time while work is underway.
-
Construction Underway on Timnath Parkway North Connection Project
Share Construction Underway on Timnath Parkway North Connection Project on Facebook Share Construction Underway on Timnath Parkway North Connection Project on X (formerly Twitter) Share Construction Underway on Timnath Parkway North Connection Project on Linkedin Email Construction Underway on Timnath Parkway North Connection Project link
Construction is now underway on the Timnath Parkway North Connection Project, a key transportation improvement that will extend Timnath Pkwy. North from the existing Buss Grove Rd. roundabout and connect it to Main St. (LCR 5). The project was approved to move into construction after Town Council awarded the construction contract at its June 23, 2026 meeting. The project is identified as a near-term priority in the Town's Transportation Master Plan and will help complete a critical connection within Timnath's roadway network.

The project includes construction of a new two-lane roadway connection, single-lane roundabout, landscaped median, shared-use path, pedestrian and bicycle improvements, and other corridor enhancements. These improvements are designed to improve safety, mobility and multimodal connectivity while supporting future growth and improving access to Main Street Timnath. When complete, the project will improve regional transportation connections, enhance access for drivers, pedestrians and cyclists, and establish. Construction is anticipated to continue through Spring 2027.
Traffic Impacts and Road Closure
As part of the project, the section of Buss Grove Road between Timnath Parkway and Main Street (LCR 5) will remain closed to traffic through approximately November 2026 while construction is completed. Motorists should plan ahead and follow posted detour routes and traffic control measures in the area. All construction schedules are subject to change. Project timelines may be affected by weather, material availability and other unforeseen conditions. The Town will provide relevant updates as project conditions and schedules evolve.

Construction is now underway on the Timnath Parkway North Connection Project, a key transportation improvement that will extend Timnath Pkwy. North from the existing Buss Grove Rd. roundabout and connect it to Main St. (LCR 5). The project was approved to move into construction after Town Council awarded the construction contract at its June 23, 2026 meeting. The project is identified as a near-term priority in the Town's Transportation Master Plan and will help complete a critical connection within Timnath's roadway network.

The project includes construction of a new two-lane roadway connection, single-lane roundabout, landscaped median, shared-use path, pedestrian and bicycle improvements, and other corridor enhancements. These improvements are designed to improve safety, mobility and multimodal connectivity while supporting future growth and improving access to Main Street Timnath. When complete, the project will improve regional transportation connections, enhance access for drivers, pedestrians and cyclists, and establish. Construction is anticipated to continue through Spring 2027.
Traffic Impacts and Road Closure
As part of the project, the section of Buss Grove Road between Timnath Parkway and Main Street (LCR 5) will remain closed to traffic through approximately November 2026 while construction is completed. Motorists should plan ahead and follow posted detour routes and traffic control measures in the area. All construction schedules are subject to change. Project timelines may be affected by weather, material availability and other unforeseen conditions. The Town will provide relevant updates as project conditions and schedules evolve.

-
Project Concept
Share Project Concept on Facebook Share Project Concept on X (formerly Twitter) Share Project Concept on Linkedin Email Project Concept link

-
Traffic Team
TOEmail traffic@timnathgov.com
-
Alternatives Analysis (December 2024)
Timnath Parkway. - Buss Grove Rd. to Main St. (CR5) has finished this stage -
Design (April 2025)
Timnath Parkway. - Buss Grove Rd. to Main St. (CR5) has finished this stage -
Construction (Summer 2026 - Spring 2027)
Timnath Parkway. - Buss Grove Rd. to Main St. (CR5) is currently at this stage