Timnath Parkway. - Buss Grove Rd. to Main St. (CR5)
The Timnath Parkway project will extend Timnath Pkwy. north from Buss Grove Rd. to reconnect with Main St. (CR5), creating an important new link in the Town’s roadway network. This connection will improve mobility, support future development, and provide residents with an new north–south travel option.
The project includes the design and construction of a new two‑lane roadway with a landscaped median and sidewalks to enhance safety and comfort for drivers, pedestrians and cyclists. The corridor will also be built to accommodate the Town’s long‑term vision for an ultimate four‑lane arterial as traffic and community needs grow.
The Timnath Parkway project will extend Timnath Pkwy. north from Buss Grove Rd. to reconnect with Main St. (CR5), creating an important new link in the Town’s roadway network. This connection will improve mobility, support future development, and provide residents with an new north–south travel option.
The project includes the design and construction of a new two‑lane roadway with a landscaped median and sidewalks to enhance safety and comfort for drivers, pedestrians and cyclists. The corridor will also be built to accommodate the Town’s long‑term vision for an ultimate four‑lane arterial as traffic and community needs grow.
-
CR 5/Main St. & Buss Grove Rd. Traffic Update (10/21)
Share CR 5/Main St. & Buss Grove Rd. Traffic Update (10/21) on Facebook Share CR 5/Main St. & Buss Grove Rd. Traffic Update (10/21) on X (formerly Twitter) Share CR 5/Main St. & Buss Grove Rd. Traffic Update (10/21) on Linkedin Email CR 5/Main St. & Buss Grove Rd. Traffic Update (10/21) link
Following unanticipated utility delays, work continues on the CR 5/Main Street and Buss Grove Road improvements.
The southbound lane reopened on Oct. 19, with work continuing in that area through Nov. 6. Additional work will continue as crews move through the remaining project items.
Weather and construction delays may impact the schedule. Please drive safely and follow posted traffic control measures.Following unanticipated utility delays, work continues on the CR 5/Main Street and Buss Grove Road improvements.
The southbound lane reopened on Oct. 19, with work continuing in that area through Nov. 6. Additional work will continue as crews move through the remaining project items.
Weather and construction delays may impact the schedule. Please drive safely and follow posted traffic control measures. -
Construction Update: Intersection Closure Scheduled for Next Phase of Work
Share Construction Update: Intersection Closure Scheduled for Next Phase of Work on Facebook Share Construction Update: Intersection Closure Scheduled for Next Phase of Work on X (formerly Twitter) Share Construction Update: Intersection Closure Scheduled for Next Phase of Work on Linkedin Email Construction Update: Intersection Closure Scheduled for Next Phase of Work link
Construction on the Timnath Pkwy. North connection is moving into the next phase, requiring a temporary closure to complete roadway improvements and prepare the area for final paving.
Beginning Sept. 28, the intersection of Buss Grove Rd. and CR 5 will be closed to all through traffic. The closure is anticipated to remain in place through Oct. 9, weather and construction conditions permitting. A signed detour route will be provided for motorists.
Following completion of this phase, the intersection is expected to reopen to traffic on a gravel surface. Final paving operations are currently scheduled for Oct. 11-16, after which the roadway will be opened in its final condition, pending weather or construction delays.
This closure is a necessary step toward completing the intersection improvements and advancing the overall project. Residents and motorists are encouraged to plan ahead and allow additional travel time while work is underway.

Construction on the Timnath Pkwy. North connection is moving into the next phase, requiring a temporary closure to complete roadway improvements and prepare the area for final paving.
Beginning Sept. 28, the intersection of Buss Grove Rd. and CR 5 will be closed to all through traffic. The closure is anticipated to remain in place through Oct. 9, weather and construction conditions permitting. A signed detour route will be provided for motorists.
Following completion of this phase, the intersection is expected to reopen to traffic on a gravel surface. Final paving operations are currently scheduled for Oct. 11-16, after which the roadway will be opened in its final condition, pending weather or construction delays.
This closure is a necessary step toward completing the intersection improvements and advancing the overall project. Residents and motorists are encouraged to plan ahead and allow additional travel time while work is underway.
-
Construction Underway on Timnath Parkway North Connection Project
Share Construction Underway on Timnath Parkway North Connection Project on Facebook Share Construction Underway on Timnath Parkway North Connection Project on X (formerly Twitter) Share Construction Underway on Timnath Parkway North Connection Project on Linkedin Email Construction Underway on Timnath Parkway North Connection Project link
Construction is now underway on the Timnath Parkway North Connection Project, a key transportation improvement that will extend Timnath Pkwy. North from the existing Buss Grove Rd. roundabout and connect it to Main St. (LCR 5). The project was approved to move into construction after Town Council awarded the construction contract at its June 23, 2026 meeting. The project is identified as a near-term priority in the Town's Transportation Master Plan and will help complete a critical connection within Timnath's roadway network.

The project includes construction of a new two-lane roadway connection, single-lane roundabout, landscaped median, shared-use path, pedestrian and bicycle improvements, and other corridor enhancements. These improvements are designed to improve safety, mobility and multimodal connectivity while supporting future growth and improving access to Main Street Timnath. When complete, the project will improve regional transportation connections, enhance access for drivers, pedestrians and cyclists, and establish. Construction is anticipated to continue through Spring 2027.
Traffic Impacts and Road Closure
As part of the project, the section of Buss Grove Road between Timnath Parkway and Main Street (LCR 5) will remain closed to traffic through approximately November 2026 while construction is completed. Motorists should plan ahead and follow posted detour routes and traffic control measures in the area. All construction schedules are subject to change. Project timelines may be affected by weather, material availability and other unforeseen conditions. The Town will provide relevant updates as project conditions and schedules evolve.

Construction is now underway on the Timnath Parkway North Connection Project, a key transportation improvement that will extend Timnath Pkwy. North from the existing Buss Grove Rd. roundabout and connect it to Main St. (LCR 5). The project was approved to move into construction after Town Council awarded the construction contract at its June 23, 2026 meeting. The project is identified as a near-term priority in the Town's Transportation Master Plan and will help complete a critical connection within Timnath's roadway network.

The project includes construction of a new two-lane roadway connection, single-lane roundabout, landscaped median, shared-use path, pedestrian and bicycle improvements, and other corridor enhancements. These improvements are designed to improve safety, mobility and multimodal connectivity while supporting future growth and improving access to Main Street Timnath. When complete, the project will improve regional transportation connections, enhance access for drivers, pedestrians and cyclists, and establish. Construction is anticipated to continue through Spring 2027.
Traffic Impacts and Road Closure
As part of the project, the section of Buss Grove Road between Timnath Parkway and Main Street (LCR 5) will remain closed to traffic through approximately November 2026 while construction is completed. Motorists should plan ahead and follow posted detour routes and traffic control measures in the area. All construction schedules are subject to change. Project timelines may be affected by weather, material availability and other unforeseen conditions. The Town will provide relevant updates as project conditions and schedules evolve.

-
Project Concept
Share Project Concept on Facebook Share Project Concept on X (formerly Twitter) Share Project Concept on Linkedin Email Project Concept link

-
Traffic Team
TOEmail traffic@timnathgov.com
-
Alternatives Analysis (December 2024)
Timnath Parkway. - Buss Grove Rd. to Main St. (CR5) has finished this stage -
Design (April 2025)
Timnath Parkway. - Buss Grove Rd. to Main St. (CR5) has finished this stage -
Construction (Summer 2026 - Spring 2027)
Timnath Parkway. - Buss Grove Rd. to Main St. (CR5) is currently at this stage